Taishan Fiberglass Zoucheng 60,000 tons Fiberglass yarn furnace main body is under construction in May

泰山邹城

2021: Taishan Fiberglass Zoucheng Co., Ltd, 60,000 tonnes fibreglass yarn furnace fiber drawing production line project progress:

March: furnace foundation construction is underway.

April: Energy assessment and soil and water conservation procedures are being handled. Foundation construction is underway, 8% of the total construction volume has been completed and is progressing steadily as planned.

May: Energy assessment underway. Foundation construction is underway and the main body of the furnace is under construction, progressing steadily according to schedule.